Port extension
Description of works
- Extension of a riprap breakwater over 360 m;
- Conversion of the basin by dredging and rock removal, to moor 700 boats;
- Construction of 140 m of floating docks in reinforced concrete
Project
- Client: Joint association to build the port of Saint Cast
- Prime contractor: Departmental Council of Cotes d’Armor
- Duration: November 2007 to October 2010
- Amount: €24,000,000 excluding tax
Distinctive features and constraints
- Tourist site (access and neighbourhood constraints)
- Exposed coastal site
Key figures
- Rock removal: 130,000 m3
- Dredging: 330,000 m3
- Riprap: 210,000 t
- Piles for floating docks: 115 u
- Reinforced concrete structures: 1600 m3
- Extension of the departmental port of Saint-Cast